Introduction
Congratulations on reaching commercial operation. Here is what to expect.
Your NYSERDA Project Manager will be reaching out shortly to touch base with you on next steps. Once the generator is registered in NYGATS and producing energy, it is important to understand the following:
- In order for all eligible generation (including test energy) to be correctly flagged Tier-1, Seller must dispute any generation that is loaded to NYGATS before the Statement of Qualification (SoQ) is issued. Contact NYGATS for assistance. If a Seller does not adhere to this requirement, NYGATS will not be required to update RECS already created. Once the SoQ has been issued, Seller and NYSERDA will coordinate with NYGATS to accept the generation for Tier 1 REC creation.
- The REC Agreement’s Contract Delivery Term usually starts the first of the month following the project’s Commercial Operation date. The NYGATS Account Holder for the project is able to sell any Tier-1 RECs pre-dating the Contract Delivery Term of its NYSERDA REC Agreement on the open market. For example, if you declare Commercial Operation and start generating electricity on August 17, the REC Agreement Contract Delivery Term will be September 1. Sellers are free to sell Tier -1 RECs generated from August 17 through August 31 to any interested party.
Instructions
Seller to review Tier 1 – Obtaining a Statement of Qualification Guide.
After receiving your SoQ, please verify that it has been uploaded to the LSR portal and notify your NYSERDA Project Manager (as indicated in the Portal project record), as this is a requirement of Operational Certification (Op Cert) for your NYSERDA REC Agreement.
Seller and NYSERDA Project Manager to schedule a Pre-Operational Certification Meeting. A typical agenda will include discussion of the following:
Operational Certification Handover Meeting
Once Operational Certification is achieved, the NYSERDA Project Manager and Seller will schedule a handover call with the NYSERDA settlements team to review the invoicing process and answer any questions.
To better understand how Index REC payments are calculated please visit Tier 1 - REC Index Pricing Structure and Calculations.
Reminders
- Once operating, be sure to provide hourly generation data on at least a quarterly basis. Send to GENDATA@nyserda.ny.gov, or contact your NYSERDA Project Manager to arrange an alternate delivery method.
- Review NYGATS Operating Rules . For questions related to your NYGATS Account, see NYGATS contacts . For questions related to Tier 1 eligibility, contact Marci.Brunner@nyserda.ny.gov or your NYSERDA Project Manager.
Be sure to refer to the current NYSERDA Project Manager listed in the Portal.