All projects from contract execution through commercial operation must submit quarterly reports through the LSR portal. Reports are due March 1, June 1, September 1, and December 1. The quarterly report consists of an updated project schedule and project narrative, plus attachments where applicable.
Updating the Project Schedule
Locate and access the project record in Salesforce. Then click the Details tab.
On the Details tab, scroll down to the Project Milestones section.
Review each numbered milestone (1-40) and update the following fields for each, as needed:
Field Name
Requirements
Description
Provide a brief status description (~1-3 sentences).
Start/End Dates
Input actual or expected dates. Start and End dates can be the same for discrete events.
Percentage Complete
Update the progress towards the milestone completion.
Creating the Project Narrative
Within the same project record, select the relevant Progress Report milestone (i.e. "Progress Report - 6/1/2021").
In the Description field, enter a brief narrative addressing updates to the following items (as well as any other pertinent details not covered by the Project Schedule updates):
Item Name
Details/Requirements
Local Outreach
Recent communication with local governments and community including organized support and opposition groups