Introduction 

All projects from contract execution through commercial operation must submit quarterly reports through the LSR portal. Reports are due March 1st, June 1st, September 1st, and December 1st. The quarterly report consists of an updated project schedule and project narrative, plus attachments where applicable.


Instructions

Info
iconfalse

All reports are due each quarter.


UI Steps
sizesmall


UI Step

Log into the Salesforce Portal and access the Projects Tab.

Expand
titlescreenshot



UI Step

Access the Project Record in Salesforce by clicking the link in the Project Name column.

Expand
titlescreenshot



UI Step

In the Project Details page, scroll down to the Document Approval/Rejection section and click the Choose File button to upload your Progress Report.

Expand
titlescreenshot


Tip
iconfalse

Continue to do this for each required attachments. Please use naming convention to match section. You can upload as many attachments as needed.



UI Step

To view what you have uploaded, click on Attachment History. Once all attachments are added, click the Save Document button to save.

Expand
titlescreenshot